Chesterfield Canal Trust - Enabling Works & TPT Bridge

A Contract Award Notice
by CHESTERFIELD CANAL TRUST LTD

Source
Contracts Finder
Type
Contract (Works)
Duration
6.5 month
Value
£1M-£3M
Sector
CONSTRUCTION
Published
30 Jan 2024
Delivery
12 Feb 2024 to 28 Aug 2024
Deadline
22 Dec 2023 13:00

Concepts

Location

Geochart for 1 buyers and 1 suppliers

1 buyer

1 supplier

Description

This Enabling Works Package is required to create safe access onto site and to divert the public to facilitate the future restoration of the canal. In summary this will include a new site entrance, site compound creation, site levelling, construction of a bridleway bridge (TPT Bridge), creation and diversion of Public Rights of Way (PROW) and the application for, obtaining of and compliance with all required permits and permissions to the extent detailed below. An overview of the works is listed below. The full Scope, including technical specification and drawings, is included in the Contract which can be found in full ITT document. Planning Conditions and Permits • Provide all necessary information for the discharge of two pre-commencement planning conditions • Application for the temporary closure and diversion of PROW • Application for a Coal Authority Permit • Contractor input for a Network Rail Permit • Application for the S278 Works Permit Scope of Works • Security of the site area to protect the public • Forming of a secure compound area and the provision of welfare facilities • Removal of tree roots and surface vegetation as identified • Tree protection as identified • Construction of the new S278 highway entrance • Excavation and reprofiling to design formation levels adjacent to the TPT Bridge • Strip existing topsoil, store and replace on reprofiled areas as identified • Testing of materials as required by the remediation strategy • Stockpiling on site of suitable excavated material • Disposal off site of any materials deemed unsuitable • Design and installation of a suitable and sufficient access road and hardstanding area to facilitate the installation of the TPT Bridge • Liaison with utility providers to agree protection measures for construction traffic within the enabling works. PROW • Construction of new temporary PROW through Network Rail land • Secure fencing to existing PROW which runs across the previously completed canal to the southern extremity of the proposed TPT bridge • Provide a secure and suitable crossing point over the above PROW • Realignment of existing footpaths and construction of new paths to link through to the new TPT Bridge - including management of the PROW's and protection of the public • Installation of new fingerboard signage for pedestrian routes TPT Bridge • Design of temporary piling platform (if required) • Excavation to formation, piling and construction of bridge foundations • Construction of abutment walls • Fabrication, delivery, assembly and installation of TPT Bridge • Surfacing and drainage to TPT Bridge and footpath approaches CDM • Fulfilment of the Principal Contractor role as defined under CDM Regulations 2015 • Fulfilment of the Principal Designer role as defined under CDM Regulations 2015 The tender documents are available from Jon Lindley. His contact details are: Email: j.lindley@chesterfield-canal-trust.org.uk Mobile: 07891624755

Award Detail

1 O Brien Contractors (Leamington Spa)
  • Value: £1,095,780

CPV Codes

  • 44212120 - Structures of bridges
  • 45100000 - Site preparation work
  • 45221110 - Bridge construction work
  • 45233125 - Road junction construction work
  • 45233161 - Footpath construction work

Indicators

  • Contract is suitable for SMEs.

Other Information

The procurement process is set out in the ITT, but will broadly consist of a single stage submission followed by an interview. Submissions will be scored in accordance with the Selection Process contained in Section 3 of the ITT. Site Visit It is highly recommended that you conduct a site visit during preparation of your submission. The Client will be hosting a site visit on 27 or 28 November 2023. This is an opportunity for all Contractors who have confirmed their intention to bid to attend site with the Client. Upon receipt of the ITT please advise if you wish to attend the Client hosted site visit and any restriction on your availability for the given dates.

Reference

Domains