PS/20/14 Surface Dressing Framework 2021-2025 (Including First Works Order 2021)

A Contract Award Notice
by EAST AYRSHIRE COUNCIL

Source
OJEU
Type
Framework (Works)
Duration
4 year (est.)
Value
£6M
Sector
CONSTRUCTION
Published
12 May 2021
Delivery
To 12 May 2025 (est.)
Deadline
n/a

Concepts

Location

East Ayrshire and South Ayrshire

Geochart for 2 buyers and 2 suppliers

2 buyers

2 suppliers

Description

Ayrshire Roads Alliance (ARA) is a shared integrated roads and transportation service established in 2014 and provides the combined roads service for East and South Ayrshire Councils. The service is delivered with the overall objective of improving the road and transportation service in both Council areas. The framework contract scope is supply and application of carriageway surface dressing or supply and application of binder only at sites within East Ayrshire and South Ayrshire. These works may include pre patching, ironwork repairs, white lining and minor screeding works etc.

Total Quantity or Scope

The framework contract scope is supply and application of carriageway surface dressing or supply and application of binder only at sites within East Ayrshire and South Ayrshire. These works may include pre-patching, ironwork repairs, white lining and minor screeding works etc. The first works order (2021) shall be included in this Invitation to Tender and shall form the basis of the framework contract/first package of works evaluation. The framework contract shall be in accordance with the rights and obligations of the employer (client) and the contractor (supplier) as regulated by the NEC4 framework contract (June 2017). Contracts awarded through the framework will be subject to the conditions of the NEC4 Engineering and Construction Short Contract (June 2017). The framework will commence early March 2021 to late February 2023 with the option to extend annually for a further 2 years. The first works order 2021 will commence 1 May 2021 and end 30 September 2021.

Award Detail

1 Kiely Bros (Birmingham)
  • Reference: ps/20/14-1
  • Num offers: 2
  • Value: £6,000,000 [share]
  • Awarded to group of suppliers.
  • Contractor is an SME.
2 John Mcquillan Contracts (Lisburn)
  • Reference: ps/20/14-1
  • Num offers: 2
  • Value: £6,000,000 [share]
  • Awarded to group of suppliers.
  • Contractor is an SME.

Award Criteria

Programme of works and risks 15.0
Fair working practice 5.0
PRICE 80.0

CPV Codes

  • 45233141 - Road-maintenance works
  • 44113810 - Surface dressing
  • 44113800 - Road-surfacing materials
  • 44113900 - Road-maintenance materials
  • 45233120 - Road construction works
  • 45233100 - Construction work for highways, roads
  • 45233140 - Roadworks
  • 45233220 - Surface work for roads

Indicators

  • Award on basis of price and quality.

Other Information

Depending on the level of competition, the Council may choose to award the framework only or the first works order only or both. This decision is at the sole discretion of East Ayrshire Council. All questions should be raised via PCS-T Messaging facility. (SC Ref:653323)

Reference

Domains