MFF 133 2022-2025 moorland restoration work sites in the Peak District and South Pennines

A Tender Notice
by PEAK DISTRICT NATIONAL PARK AUTHORITY

Source
Find a Tender
Type
Contract (Works)
Duration
31.5 month
Value
2M
Sector
ENVIRONMENT
Published
26 Apr 2022
Delivery
18 Jul 2022 to 31 Mar 2025
Deadline
25 May 2022 17:00

Concepts

Location

Peak District National Park and South Pennines

Geochart for 2 buyers and 0 suppliers

Description

1. The objective of this Contract is to deliver a suite of Works on 17 upland Sites in the Peak District and South Pennines SAC. The sites are split into 9 packages of work. The aim of the Works suites are to stabilise and revegetate bare peat, restore hydrology, and increase biodiversity on the Sites. 2. The Works comprise the following tasks: a. Supply and delivery of Materials required to complete the Works, unless otherwise stated. b. Appropriate storage of Materials, as necessary. c. Supply and delivery of suitable Trackway for storing materials on (see Packages if required). d. Forwarding of Materials and Equipment required to complete the Works to and within Works Sites, excluding Airlifting e. Planning the Aerial Load Lifting Works, including marking out drop locations and working in collaboration with the Authorities Airlifting Contractor to deliver the works f. Marshalling of Aerial Load Lifting, including materials drops g. Installation of Stone Dams into gullies h. Installation of Peat Dams into gullies i. Installation of Peat Bunding j. Re-profiling of hags and gully sides

Lot Division

1 Chellow Whole Site works pacakge
  • Duration: 7.5 month

a. The objective of this works package is the delivery of various works on multiple works sites across the Chellow water treatment works catchment. b. The works include: i. The supply, cutting & spreading of heather brash ii. Receiving delivery of initial & maintenance lime, seed & fertiliser & application by hand to bare peat areas iii. The supply & construction of stone dams & coir log dams For details of quantities and location please see the Invitation to Tender (appendix 1) iv. The supply & installation of temporary trackway at Thornton Lift Site v. The construction of peat dams & re-profiling of gully systems vi. The planting of sphagnum moss plug plants vii. Heather cutting for diversification viii. Landscaping of 65 metres of bridleway ix. The marshalling of all aerial load lifting operations required for the works

2 Twizle Head Whole Site Works package
  • Duration: 19.5 month

Brash (Bags) 443 Lime, Seed & Fertiliser (total) ha 2.17 Year 2 Lime and Fertiliser (total) ha 2.17 Re-profiling (m) 10344 Sedge/dwarf shrub Plug plants for Brash (@10,000 per ha) (ha) 2.17 Sedge/dwarf shrub Plug plants (@2,500 per ha) (ha) 2.83 Grip/Gully Blocking: Peat Dam (units) 309 Grip/Gully Blocking: Timber Dam (units) 227 Grip/Gully Blocking: Stone Dam (units) 355

3 Longwood Catchment (Deanhead, Close Moss, Cupwith Hill Pule, Bobus, Wessenden) Whole Sites Package
  • Duration: 19.5 month

Brash, bunding, application of lime seed and fertiliser, maintenance of lime seed and fertiliser, re-profiling, sphagnum planting, planting of shrub plug plants, grip/gully blocking (peat, low peat, timber, stone & coir), molina cutting and heath cutting in quantities For more detail on quantities and location please see the Invitation to Tender (appendix 3).

4 Soyland
  • Duration: 19.5 month

Grip/Gully Blocking - Peat (Dam unit) 719 Grip/Gully Blocking - Timber (Dam unit) 22 Grip/Gully Blocking: Heather Bales 399 Grip/Gully Blocking - Stone (Dam unit) 113 Bunding (ha) 36 Re-profiling (m) 178

5 Rishworth
  • Duration: 31.5 month

Grip/Gully Blocking - Stone (Dam unit) 32 Grip/Gully Blocking: Heather (Bale) 82 Grip/Gully Blocking: Peat Dam (units) 298 Molinia Cutting (ha) 16.5 Re-profiling (m) 84 Bunding (ha) 26.35 Heather brash (bags) 33 Initial lime, seed and fertiliser (ha) 0.23 Maintenance lime and fertiliser 0.16 Standard Sphagnum planting (@1250 per ha) (ha) 54 Sedge/dwarf shrub Plug plants (@2,500 per ha) (ha) 28

6 Turley Holes
  • Duration: 31.5 month

Peat Bunding (ha) 1.905 Grip/Gully Blocking: Peat Dam (Dam unit) 132 Grip/Gully Blocking: Heather (Bale) 468 Grip/Gully Blocking: Stone (Dam unit) 29 Re-profiling (m) 281

8 Pikenaze whole Site Works Package
  • Duration: 30.5 month

Geotextile (m2) 21,482 Lime, Seed & Fertiliser (ha) 2.20 Year 2 Lime and Fertiliser (ha) 2.20 Re-profiling (m) 12,259 Sedge/dwarf shrub Plug plants for Geotextile (@10,000 per ha) (ha) 2.15 Gully Blocking: Stone (Dam Units) 122 (91.5 tonnes, at 94 locations)

8 Snailsden whole works site package
  • Duration: 30.5 month

Description/lot 7 quantites/lot 7a quantities Brash (Bags)/ -/ 963 Lime, Seed & Fertiliser (ha)/ -/ 4.75 Year 2 Lime and Fertiliser (ha)/ -/ 4.75 Seed into sward (ha)/ -/ 3.35 Seed onto bare peat (ha)/ -/ 0.02 Bunding (ha)/ 10.32/ - Re-profiling (m)/ -/ 23,339 Pool mix Sphagnum into existing pools (@8000 per ha) (ha)/ -/ 0.72 Sphagnum planting (@1250 per ha) (ha)/ -/ 398.4 Sedge/dwarf shrub Plug plants for Brash (@10,000 per ha) (ha)/ -/ 4.72 Sedge/dwarf shrub Plug plants (dry mix) (@2,500 per ha) (ha)/ -/ 23.18 Sedge/dwarf shrub Plug plants (wet mix) (@2,500 per ha) (ha) /-/ 0.08 Grip/Gully Blocking: Coir Logs (Coir logs)/ -/ 122 Grip/Gully Blocking: Peat (Dam)/ 1961/ 654 Grip/Gully Blocking: Timber (Dam)/ 81/ 326 Grip/Gully Blocking: Stone (Dam)/ 362/ 1449 Heather Cutting (ha)/ -/ Up to 23 ha

CPV Codes

  • 45262640 - Environmental improvement works

Indicators

  • Bids should cover one or more lots.
  • Bids should cover the whole contract.
  • Renewals are not available.
  • Award on basis of price and quality.