Description

National Highways continues to roll out the Asset Delivery model to its operational areas. There is a requirement to deliver a range of renewal, improvement and selected small scheme construction works on the Strategic Road Network in areas utilising specialist contractors working collaboratively with National Highways to deliver these works. It is envisaged that this framework will straddle two Road Investment Strategy (RIS) periods (RIS 2 and RIS 3) enabling a smooth transition between them. Works for schemes have been divided into a number of workstreams that align with the contractors' specialisms, and will also include design. Bandings have been introduced into the framework model to differentiate some contracting terms between bands. This award is for Lot 1.1 General Civil Engineering (super region) in the South region (National Highways Areas 1, 2, 3 and 4) This Lot covers the supply of materials, plant and labour to carry out construction and removal activities, including but not limited to; - Highway drainage assets - Pipes, - Ditches, - Swales, - Ponds, - The control and disposal of contaminated material, - The installation of traffic signs and posts, - Non-illuminated traffic signs and posts - Earthworks, - Ducting, - Kerbing, - Footways, - Modular paving, - Site clearance, - Brick, block and stonework, - Piling, - Temporary works required to ensure a safe method of working. - Demolition - Concrete, - Asbestos removal (planned) - Earthwork stabilisation, - Counterfort drains, - Soil nailing - Ground anchors - Slope netting (rock and soil), - Rock slope works including dowels, bolts, scaling, buttressing, dentition, shotcrete, and - 'Innovative' stabilisation techniques, such as electrokinetic osmosis, fibre reinforced soil, soil mixing and the use of geosynthetics to reinforce soil Other duties This scope also includes: - Mobilisation - Early Contractor Involvement - Elements of Supplier Design - Principal contractor - Welfare facilities - Manage Network Occupancy - Community; and - Contingency The scope may also include carrying out some of the duties of the Maintenance & Response Contractor and providing Incident Response Rapid Response) when instructed.

Award Detail

1 Eurovia Infrastructure (Horsham)
  • Value: £144,453,487

CPV Codes

  • 45000000 - Construction work

Indicators

  • Contract is suitable for SMEs.

Other Information

n/a Eurovia 1.1_S SDF Lot 1 Form of Agreement Signed_Redacted.pdf n/a SDF ECC Contract Data - Part 1 CONTRACT Issue 1 Rev 0_Redacted.pdf n/a SDF Framework Contract Data Part 2 - Issue 01 Rev 2 Blank.docx n/a SDF ECC Contract Data Part 2 Issue 01 Rev 4 Blank.docx n/a SDF ECC Scope Annex 1 Cost Capture Data Requirements CONTRACT Issue 1 Rev 0.pdf n/a SDF ECC Scope Annex 2 Community CONTRACT Issue 1 Rev 0.pdf n/a SDF ECC Scope Annex 3 Communications CONTRACT Issue 1 Rev 0.pdf n/a SDF ECC Scope Annex 4 Customer Service CONTRACT Issue 1 Rev 0.pdf n/a SDF ECC Scope Annex 5 Client Requirements CONTRACT Issue 1 Rev 0.pdf n/a SDF ECC Scope Annex 6 Insurance Requirements CONTRACT Issue 1 Rev 0.pdf n/a SDF ECC Scope CONTRACT Issue 1 Rev 0.pdf n/a SDF FI Appendix 1 Defined Terms CONTRACT Issue 1 Rev 0.pdf n/a SDF FI Appendix 10 Health and Safety CONTRACT Issue 1 Rev 0.pdf n/a SDF FI Appendix 11 Performance Management CONTRACT Issue 1 Rev 0.pdf n/a SDF FI Appendix 12 Continual Improvement CONTRACT Issue 1 Rev 0.pdf n/a SDF FI Appendix 13 Environmental Management & Sustainability CONTRACT Issue 1 Rev 0.pdf n/a SDF FI Appendix 14 Data Protection CONTRACT Issue 1 Rev 0.pdf n/a SDF FI Appendix 15 Allocation Procedure CONTRACT Issue 1 Rev 0.pdf n/a SDF FI Appendix 2 Reference Documents CONTRACT Issue 1 Rev 0.pdf n/a SDF FI Appendix 3 Vision CONTRACT Issue 1 Rev 0.pdf n/a SDF FI Appendix 4 Quality Management CONTRACT Issue 1 Rev 0.pdf n/a SDF FI Appendix 5 Information Systems Security CONTRACT Issue 1 Rev 0.pdf n/a SDF FI Appendix 6 Clients personnel security procedures CONTRACT Issue 1 Rev 0.pdf n/a SDF FI Appendix 7 PCG CONTRACT Issue 1 Rev 0.pdf n/a SDF FI Appendix 8 FoN Client to Client CONTRACT Issue 1 Rev 0.pdf n/a SDF FI Appendix 9 FoN Supplier to Supplier CONTRACT Issue 1 Rev 0.pdf n/a SDF Framework Contract Data Part 1 CONTRACT Issue 1 Rev 0.pdf n/a SDF Framework Information CONTRACT Issue 1 Rev 0.pdf n/a SDF Specification CONTRACT Issue 1 Rev 0.pdf

Reference

Domains