RHP Lot 1 - Repairs, Voids and Planned Works Contracts. RHP Lot 2 - 3* Gas, Gas and Electric Compliance Contract
A Contract Award Notice
by ECHELON CONSULTANCY LTD
- Source
- Contracts Finder
- Type
- Contract (Works)
- Duration
- 10 year
- Value
- £42M-£155M
- Sector
- CONSTRUCTION
- Published
- 21 Jul 2023
- Delivery
- 02 Jun 2023 to 01 Jun 2033
- Deadline
- 11 Apr 2022 11:00
Concepts
Location
1 buyer
- Echelon Consultancy Teddington
2 suppliers
- Kier Places Salford
- Smith & Byford Cheam
Description
RHP sought expressions of interest from suitably skilled and experienced suppliers for the delivery of repairs, voids, planned work (planned works is an optional addition year on year), 3* gas, gas and electric compliance works across its stock. The contract was initially procured as three Lots; Lot 1 - repairs, voids and planned works, Lot 2 - 3* gas, gas and electric compliance and Lot 3 - integrated asset management contract (combination of Lots 1 & 2). Participants could apply for all or any of Lots 1 to 3. Participants were asked to note that if Lot 3 was awarded, Lots 1 and 2 would not be awarded and if Lots 1 & 2 were awarded as separate contracts then Lot 3 would not be awarded. During the procurement process it was determined that RHP would proceed with Lot 1 and Lot 2 only, and as such Lot 3 was abandoned at the end of the ISDS stage. During the procurement process for Lot 1, it was decided that RHP would create a WOS for the delivery of work under this Lot. Lot 2 progress as a standard outsourced contract.
Award Detail
1 | Kier Places (Salford)
|
2 | Smith & Byford (Cheam)
|
CPV Codes
- 45000000 - Construction work
Indicators
- Contract is suitable for SMEs.
- Contract is suitable for VCOs.
Other Information
RHP followed a three-stage Competitive Dialogue procurement process in accordance with the Public Contract Regulations 2015. Under the first stage of the process, prospective bidders were required to complete a Selection Questionnaire and its associated appendices. Following evaluation of submitted SQ's, RHP anticipated shortlisting six bidders to be Invited to Submit Detailed Solutions under the second stage of the process. Following evaluation of received ISDS submissions, RHP anticipated shortlisting three Tenderers to be invited to participate in Competitive Dialogue and submit Final Tenders. Following evaluation of Final Tenders, RHP intended to award the contract to two single contractors for Lots 1 & 2 as separate contracts or Lot 3 to a single contractor as a single contract. Full details of the requirements and instructions are included in the procurement and Tender documents.
Reference
- 20230721164355-45191
- CF f1397df6-f4d9-4de4-b252-153f3e94fc91