ISO 11 Incinerator Life Extension Project - WP10 Hydraulic System Replacement Project

A Tender Notice
by THE PIRBRIGHT INSTITUTE

Source
Contracts Finder
Type
Contract (Works)
Duration
10 month
Value
£45K-£50K
Sector
INDUSTRIAL
Published
31 Oct 2024
Delivery
03 Feb 2025 to 28 Nov 2025
Deadline
13 Dec 2024 12:00

Concepts

Location

Geochart for 1 buyers and 0 suppliers

1 buyer

Description

The scope of works will involve: • Detailed design work for the hydraulic system, with all calculations (tank sizing, pump sizing, pipe pressure loss, etc) • Supply, manufacture, delivery and installation of the hydraulic system • Overhaul of existing hydraulic rams • Remove the existing hydraulic system and drain all oil into suitable containers. • Install the new hydraulic system and connect to the overhauled rams • Commissioning of hydraulic system in isolation of the control panel. • Final commissioning with the control panel providing the enabling/disabling signals. • During the works, the existing hydraulic system and drained oil will remain in the loading hall area. The site team will arrange for this to be taken outside of containment. However, the supplier is to allow costs for: o Draining all oil from the hydraulic system into suitable containers o Dismantling the existing hydraulic system so it can be taken out of the fire door (approx. 900mm wide) o Lift and shift of all items outside of biocontainment o Disposal of existing hydraulic system and provide all waste certification to the Client Project Manager • Management of all subcontractors employed by the supplier to complete these works. • On completion, an O&M is to be submitted which provides details of works from design to completion. The O&M should include all relevant items shown in the PIF and should include all valves/components labelled with a schedule of components included. A separate section which provides details of the following o Brief Description of the works being carried out. o Project Risk Assessment. o Key structural principals. o Hazardous materials used. o Information on the future removal of installed plant. o H&S information about equipment provided for cleaning or maintaining installed plant. o The nature, location and markings of significant services. o Information and as built drawings of buildings, plant and equipment. o Step by step activities to carry out the works. o Lesson Learnt, challenges met and how they were overcome. • As part of the works, the supplier should also provide the following: o All provisions for the installation and deconstruction work, including but not limited to: • All necessary machinery and equipment required for the works. • Provision of lighting if needed during winter months • Provision of transport vehicles required for the works which is not listed as part of the CDM site below. • Provision of weather protection for any equipment and materials used/stored outside. • All PPE required for safe working during all works. A CDM Construction site will be set up as part of the overall project which will provide for the following: • Site Supervision • HERRAS fencing and appropriate signage around CDM area • Site Office • Welfare Office including changing areas • Waste skips • Scissor lift • Fork-lift truck / telehandler • CDM documentation / inductions / daily logs / management of RAMS

CPV Codes

  • 42121000 - Hydraulic or pneumatic power engines and motors
  • 42122210 - Hydraulic power packs
  • 42320000 - Waste incinerators
  • 71310000 - Consultative engineering and construction services
  • 71320000 - Engineering design services

Indicators

  • Contract is suitable for SMEs.

Other Information

Please note that Appendix H - Confidentiality Agreement must be fully completed, signed, PDFed and emailed to Procurement.Department@pirbright.ac.uk asap. Then and only then will access to the full ITT package (6. Appendix E1 - Site Documents & 6. Appendix E2 - Existing Hydraulic System O&M) be granted to the requester. 1. ITT - WP10 Hydraulic System Replacement Project.docx 2. Appendix A - Supplier Pre-Qualification Questionnaire.docx 3. Appendix B - Scoring Matrix V1.xlsx 4. Appendix C - Pricing Schedule.xlsx 5. Appendix D - NEC4 ECC OpA Contract Data.docx 6. Appendix E - WP10 Hydraulic System Replacement Project.docx 7. Appendix F - Form of Offer.docx 8. Appendix G - The Pirbright Institutes use of animals in research.pdf 9. Appendix H - Confidentiality Agreement.docx

Reference

Domains