Environmental Planning for Nuclear Decommissioning at Hartlepool, Heysham 1 and Dungeness B Power Station

A Tender Notice
by EDF ENERGY NUCLEAR GENERATION LIMITED ("EDF")

Source
Find a Tender
Type
Contract (Services)
Duration
7 year
Value
£4M
Sector
ENVIRONMENT
Published
24 Aug 2021
Delivery
To 05 Mar 2029 (est.)
Deadline
23 Sep 2021 11:00

Concepts

Location

Heysham 1 Power Station Morecambe Lancashire LA3 2XH

Geochart for 1 buyers and 0 suppliers

Description

EDF wishes to procure the provision of professional services to prepare and submit Environmental Impact Assessment for Decommissioning Regulations (EIADR) and Town and Country Planning Act (TCPA) planning applications, as well as other supporting assessments and documents, for the new waste management facilities at Heysham 1 Power Station, Hartlepool Power Station and Dungeness B Power Station. Furthermore, the scope of professional services also includes the preparation of an environmental statement for the decommissioning project under EIADR. A summary of the key scope elements requirements of this Service is comprised of the following key elements set out below: 1. Planning 2. Consultation and Engagement 3. Environmental Impact Assessment (EIA) 4. Marine Licence Applications This procurement is a competitive two-stage process to be conducted in accordance with the Restricted Procedure. Further details are provided in the procurement documents which are available upon registering an interest in this opportunity via Ivalua.

Lot Division

1 Environmental Planning for Nuclear Decommissioning at Heysham 1 Power Station
  • Value: £1M

EDF wishes to procure the provision of professional services to prepare and submit planning and EIADR applications, as well as other supporting assessments and documents, for the new waste management facilities at Heysham 1 Power Station. A summary of the key scope elements requirements of this Service is comprised of the following key elements set out below: Planning: Planning permission is required from each relevant Local Planning Authority (LPA) under the TCPA to enable the construction and commission of each of the three waste management facilities. As part of this, planning advice on the scope of civil works, preparation of the planning application (including the planning statement and design and access statements), support during the application determination and post determination in discharging planning conditions will be required. Consultation and Engagement: Support is required in consultation and event management to support both TCPA and EIADR applications, including preparing consultation material, online and virtual engagement platforms, and data management in accordance with the General Data Protection Regulation requirements. The preparation of Consultation Plans and Consultation Reports is also required. Environmental Impact Assessment (EIA): The potential environmental impacts of the decommissioning work has to be assessed through the EIA process, with appropriate Environmental Statements (ES) being submitted with each application for permission, as required by the TCPA EIA Regulations and the EIADR. Marine Licence Applications: Some civil works associated with the waste management facilities and decommissioning works in the marine environment may also require a Marine Licence under the Marine and Coastal Access Act. Further details are provided in the Invitation to Tender documents which are available upon registering an interest in this opportunity via Ivalua

2 Environmental Planning for Nuclear Decommissioning at Hartlepool Power Station
  • Value: £1M

EDF wishes to procure the provision of professional services to prepare and submit planning and EIADR applications, as well as other supporting assessments and documents, for the new waste management facilities at Hartlepool Power Station. A summary of the key scope elements requirements of this Service is comprised of the following key elements set out below: Planning: Planning permission is required from each relevant Local Planning Authority (LPA) under the TCPA to enable the construction and commission of each of the three waste management facilities. As part of this, planning advice on the scope of civil works, preparation of the planning application (including the planning statement and design and access statements), support during the application determination and post determination in discharging planning conditions will be required. Consultation and Engagement: Support is required in consultation and event management to support both TCPA and EIADR applications, including preparing consultation material, online and virtual engagement platforms, and data management in accordance with the General Data Protection Regulation requirements. The preparation of Consultation Plans and Consultation Reports is also required. Environmental Impact Assessment (EIA): The potential environmental impacts of the decommissioning work has to be assessed through the EIA process, with appropriate Environmental Statements (ES) being submitted with each application for permission, as required by the TCPA EIA Regulations and the EIADR. Marine Licence Applications: Some civil works associated with the waste management facilities and decommissioning works in the marine environment may also require a Marine Licence under the Marine and Coastal Access Act. Further details are provided in the Invitation to Tender documents which are available upon registering an interest in this opportunity via Ivalua

3 Environmental Planning for Nuclear Decommissioning at Dungeness B Power Station
  • Value: £1M

EDF wishes to procure the provision of professional services to prepare and submit planning and EIADR applications, as well as other supporting assessments and documents, for the new waste management facilities at Dungeness B Power Station. A summary of the key scope elements requirements of this Service is comprised of the following key elements set out below: Planning: Planning permission is required from each relevant Local Planning Authority (LPA) under the TCPA to enable the construction and commission of each of the three waste management facilities. As part of this, planning advice on the scope of civil works, preparation of the planning application (including the planning statement and design and access statements), support during the application determination and post determination in discharging planning conditions will be required. Consultation and Engagement: Support is required in consultation and event management to support both TCPA and EIADR applications, including preparing consultation material, online and virtual engagement platforms, and data management in accordance with the General Data Protection Regulation requirements. The preparation of Consultation Plans and Consultation Reports is also required. Environmental Impact Assessment (EIA): The potential environmental impacts of the decommissioning work has to be assessed through the EIA process, with appropriate Environmental Statements (ES) being submitted with each application for permission, as required by the TCPA EIA Regulations and the EIADR. Marine Licence Applications: Some civil works associated with the waste management facilities and decommissioning works in the marine environment may also require a Marine Licence under the Marine and Coastal Access Act. Further details are provided in the Invitation to Tender documents which are available upon registering an interest in this opportunity via Ivalua

CPV Codes

  • 90712000 - Environmental planning
  • 71313440 - Environmental Impact Assessment (EIA) services for construction
  • 79416200 - Public relations consultancy services
  • 90711400 - Environmental Impact Assessment (EIA) services other than for construction

Indicators

  • Restrictions apply to the lot award allocation.
  • This is a one-off contract (no recurrence)
  • Renewals are not available.
  • Professional qualifications are sought.
  • Staff qualifications are relevant.

Other Information

** PREVIEW NOTICE, please check Find a Tender for full details. ** Tenderers must register on Ivalua in order to access the procurement documents using the link https://pha.edf.com/page.aspx/en/usr/login. When you have registered please access 'Public RFx' and search for 'RFx_101060'. Prior to any procurement documents being accessible to tenderers, they will need to review, understand and agree to the confidentiality agreement as part of the Ivalua registration process. If a tenderer is unable to accept the confidentiality agreement, they will automatically be excluded from the procurement process. A supply chain briefing event is to be held on 1 September 2021. The call will be held on Zoom. Instructions for joining this call are included within the procurement documents which will be available on registration to the Ivalua system and acceptance to the confidentiality agreement as part of the Ivalua registration process. This procurement relates to a subsidised contract under Regulation 13 of the PCR and will therefore be carried out in accordance with Part 2 of the PCR. EDF expressly reserves the right: - not to award any contract for one or more lots as a result of the procurement process commenced by publication of this notice; - to make whatever changes it may see fit to the content and structure of the procurement process. In no circumstances will EDF be liable for any bid costs incurred by tenderers.