Environmental Planning for Nuclear Decommissioning at Hartlepool, Heysham 1 and Dungeness B Power Stations

A Contract Award Notice
by E D F ENERGY

Source
Find a Tender
Type
Contract (Services)
Duration
7 year (est.)
Value
£4M-£4M
Sector
ENVIRONMENT
Published
11 Apr 2022
Delivery
To 05 Mar 2029 (est.)
Deadline
n/a

Concepts

Location

GLOUCESTER

Geochart for 2 buyers and 3 suppliers

2 buyers

1 supplier

Description

The provision of professional services to prepare and submit Environmental Impact Assessment for Decommissioning Regulations (EIADR) and Town and Country Planning Act (TCPA) planning applications, as well as other supporting assessments and documents, for the new waste management facilities at Heysham 1 Power Station, Hartlepool Power Station and Dungeness B Power Station. A summary of the key scope elements requirements of this Service is comprised of the following key elements set out below: 1. Planning 2. Consultation and Engagement 3. Environmental Impact Assessment (EIA) 4. Marine Licence Applications

Lot Division

1 Environmental Planning for Nuclear Decommissioning at Heysham 1 Power Station

The provision of professional services to prepare and submit planning applications, as well as other supporting assessments and documents, for the new waste management facilities at Heysham 1 Power Station. The scope of professional services also includes the preparation of an environmental statement for the decommissioning project under the Environmental Impact Assessment for Decommissioning Regulations (EIADR). A summary of the key scope elements requirements of this Service is comprised of the following key elements set out below: Planning: Planning permission is required from each relevant Local Planning Authority (LPA) under the TCPA to enable the construction and commission of each of the three waste management facilities. As part of this, planning advice on the scope of civil works, preparation of the planning application (including the planning statement and design and access statements), support during the application determination and post determination in discharging planning conditions will be required. Consultation and Engagement: Support is required in consultation and event management to support both TCPA and EIADR applications, including preparing consultation material, online and virtual engagement platforms, and data management in accordance with the General Data Protection Regulation requirements. The preparation of Consultation Plans and Consultation Reports is also required. Environmental Impact Assessment (EIA): The potential environmental impacts of the decommissioning work has to be assessed through the EIA process, with appropriate Environmental Statements (ES) being submitted with each application for permission, as required by the TCPA EIA Regulations and the EIADR. Marine Licence Applications: Some civil works associated with the waste management facilities and decommissioning works in the marine environment may also require a Marine Licence under the Marine and Coastal Access Act.

2 Environmental Planning for Nuclear Decommissioning at Hartlepool Power Stations

The provision of professional services to prepare and submit planning applications, as well as other supporting assessments and documents, for the new waste management facilities at Hartlepool Power Station. The scope of professional services also includes the preparation of an environmental statement for the decommissioning project under the Environmental Impact Assessment for Decommissioning Regulations (EIADR). A summary of the key scope elements requirements of this Service is comprised of the following key elements set out below: Planning: Planning permission is required from each relevant Local Planning Authority (LPA) under the TCPA to enable the construction and commission of each of the three waste management facilities. As part of this, planning advice on the scope of civil works, preparation of the planning application (including the planning statement and design and access statements), support during the application determination and post determination in discharging planning conditions will be required. Consultation and Engagement: Support is required in consultation and event management to support both TCPA and EIADR applications, including preparing consultation material, online and virtual engagement platforms, and data management in accordance with the General Data Protection Regulation requirements. The preparation of Consultation Plans and Consultation Reports is also required. Environmental Impact Assessment (EIA): The potential environmental impacts of the decommissioning work has to be assessed through the EIA process, with appropriate Environmental Statements (ES) being submitted with each application for permission, as required by the TCPA EIA Regulations and the EIADR. Marine Licence Applications: Some civil works associated with the waste management facilities and decommissioning works in the marine environment may also require a Marine Licence under the Marine and Coastal Access Act.

3 Environmental Planning for Nuclear Decommissioning at Dungeness B Power Station

The provision of professional services to prepare and submit planning applications, as well as other supporting assessments and documents, for the new waste management facilities at Dungeness B Power Station. The scope of professional services also includes the preparation of an environmental statement for the decommissioning project under the Environmental Impact Assessment for Decommissioning Regulations (EIADR). A summary of the key scope elements requirements of this Service is comprised of the following key elements set out below: Planning: Planning permission is required from each relevant Local Planning Authority (LPA) under the TCPA to enable the construction and commission of each of the three waste management facilities. As part of this, planning advice on the scope of civil works, preparation of the planning application (including the planning statement and design and access statements), support during the application determination and post determination in discharging planning conditions will be required. Consultation and Engagement: Support is required in consultation and event management to support both TCPA and EIADR applications, including preparing consultation material, online and virtual engagement platforms, and data management in accordance with the General Data Protection Regulation requirements. The preparation of Consultation Plans and Consultation Reports is also required. Environmental Impact Assessment (EIA): The potential environmental impacts of the decommissioning work has to be assessed through the EIA process, with appropriate Environmental Statements (ES) being submitted with each application for permission, as required by the TCPA EIA Regulations and the EIADR. Marine Licence Applications: Some civil works associated with the waste management facilities and decommissioning works in the marine environment may also require a Marine Licence under the Marine and Coastal Access Act.

Award Detail

1 AECOM (London)
  • Environmental Planning for Nuclear Decommissioning at Heysham 1 Power Station
  • Num offers: 5
  • Value: £1,249,658.78-£1,483,182
2 AECOM (London)
  • Environmental Planning for Nuclear Decommissioning at Hartlepool Power Station
  • Num offers: 5
  • Value: £1,199,756.45-£1,462,640
3 AECOM (London)
  • Environmental Planning for Nuclear Decommissioning at Dungeness B Power Station
  • Num offers: 5
  • Value: £1,074,295.61-£1,241,395

Award Criteria

Quality 70.0
Commercial 30.0

CPV Codes

  • 90712000 - Environmental planning
  • 71313440 - Environmental Impact Assessment (EIA) services for construction
  • 79416200 - Public relations consultancy services
  • 90711400 - Environmental Impact Assessment (EIA) services other than for construction

Indicators

  • Award on basis of price and quality.