Description

The University of Sheffield's Translational Energy Research Centre (TERC) is one of the largest and best-equipped national R&D centres in Europe for zero-carbon energy, hydrogen, bioenergy, and Carbon Capture, Utilisation and Storage (CCUS). We are looking to procure a sustainable aviation fuel (SAF) pilot plant based on Fischer-Tropsch technology. The plant will be required to produce at least 1.5 litres/h of sustainable aviation fuel to Jet A-1 ASTM specification D1655 (with flash point minimum of 38°C and a freeze point maximum of -47°C). The SAF plant will utilise CO2 extracted from bioenergy exhaust gases and on-site generated green H2 as feedstocks. It will also have the option to use biomass syngas from an onsite gasifier.

Lot Division

2 Reverse Water Gas Shift (RWGS) module
  • Value: £800K

The tender is for a full turn-key solution including: design, build, installation and commissioning of all elements of the plant from cleaning and preparation of the feed gases, through to conversion of CO2 and H2 to syngas; reaction of the syngas in an FT reactor; and product upgrading steps to achieve the desired product. The selected tenderer will be the Principal Designer and the Principal Contractor for the project with respect to CDM regulations.

3 Blending Skid
  • Value: £100K

The tender is for a full turn-key solution including: design, build, installation and commissioning of all elements of the plant from cleaning and preparation of the feed gases, through to conversion of CO2 and H2 to syngas; reaction of the syngas in an FT reactor; and product upgrading steps to achieve the desired product. The selected tenderer will be the Principal Designer and the Principal Contractor for the project with respect to CDM regulations.

4 Fischer Tropsch reactor
  • Value: £1M

The tender is for a full turn-key solution including: design, build, installation and commissioning of all elements of the plant from cleaning and preparation of the feed gases, through to conversion of CO2 and H2 to syngas; reaction of the syngas in an FT reactor; and product upgrading steps to achieve the desired product. The selected tenderer will be the Principal Designer and the Principal Contractor for the project with respect to CDM regulations.

5 Hydrocracking and hydrogeneration reactor
  • Value: £900K

As described within the tender documents

6 Distillation module
  • Value: £180K

As described within the tender documents

7 Online process analyser
  • Value: £100K

As described within the tender documents

7 Feed gas clean up and conditioning module
  • Value: £250K

The tender is for a full turn-key solution including: design, build, installation and commissioning of all elements of the plant from cleaning and preparation of the feed gases, through to conversion of CO2 and H2 to syngas; reaction of the syngas in an FT reactor; and product upgrading steps to achieve the desired product. The selected tenderer will be the Principal Designer and the Principal Contractor for the project with respect to CDM regulations.

8 Biomass syngas clean upand conditioning module (as add-on to Lot 1A)
  • Value: £125K

The tender is for a full turn-key solution including: design, build, installation and commissioning of all elements of the plant from cleaning and preparation of the feed gases, through to conversion of CO2 and H2 to syngas; reaction of the syngas in an FT reactor; and product upgrading steps to achieve the desired product. The selected tenderer will be the Principal Designer and the Principal Contractor for the project with respect to CDM regulations.

Renewal Options

As described within the tender documents

CPV Codes

  • 09000000 - Petroleum products, fuel, electricity and other sources of energy
  • 38970000 - Research, testing and scientific technical simulator
  • 73000000 - Research and development services and related consultancy services

Indicators

  • Restrictions apply to the lot award allocation.
  • Bids should cover one or more lots.
  • Bids should cover the whole contract.
  • Options are available.
  • Renewals are not available.
  • Professional qualifications are sought.
  • Award on basis of price and quality.

Reference

Domains